General Lighting Request at Intersection Of Morton St & American Legion Hwy, Dorchester
Meet contractor @ Moton St overpass, to splice and insulate connections, coming from new conduit that'll light up the underpass lighting.
CLOSED
Resolved. Spliced and insulated all connections and tested. All lights working. RE, EP. -
5 months ago
#101004222356
|
|
General Lighting Request at Intersection Of Morton St & American Legion Hwy, Dorchester
PLEASE SPLICE NEW EVERSOURCE CABLES IN S.L.C.B.#1825LOCATED ON AMERICAN LEGIN HWY OPPOSITE MORTON ST RAMP REMOVE SYSTEM FROM TIE CONNECTION S.L.C.B.#1826 RETURN TO NORMAL OPERATION | Problem: [Other]
CLOSED
Case Resolved. TIED IN EVERSOURSE FEED TO S.L.C.B.# 1825 AND ALSO TIED IN DISTRIBUTION PULL BOX TO FEED SYSTEM. CUT AWAT AND MADE SAFE TIE CONNECTION AT S.L.C.B. 1826 AND PUTH BOTH SYSTEMS BACK ON LINE INDEPENDINTLY. ***** S.L.C.B. 1825 HAS NO CONTROL POLE OR CONTROL CIRCUT SYSTEM LEFT ON CONSTANT , S.L.C.B. 1826 BACK ON LINE AND IN NORMAL OPERATION MODE ******. R.ELLINGTOON / S.RIED / N.MUSTACCHIO. -
6 months ago
#101004197865
|
|
|
General Lighting Request at Intersection Of Morton St & American Legion Hwy, Dorchester
Install panel board in SLCB. Excavate the side of the control box, to expose 3" conduit. Add a section of 3" conduit, as a riser. Snake and pull #4 cables as needed, so Eversource can pull a new service from their manhole to our control...
CLOSED
Resolved. Installed one panel board in our SLCB. Excavated the side of the control box and exposed the existing section of 3" conduit. Mounted a ten foot section of 3" conduit, as a riser. Snaked and pulled #4 cables, from roadway pull box, into the control cabenit and another three #4 cables, from the control cabenit, up the riser, so Eversource can splice in the new service. Cables are dead ended and taped up, in the controller and pull box, until Eversource energizes them. RE, EP. -
6 months ago
#101004173597
|
|
|
General Lighting Request at Intersection Of Williams St & Forest Hills St, Jamaica Plain
Guide cable down on ground. 802L
CLOSED
Resolved. CIT away cable. Area safe. 802L. -
10 months ago
#101004025580
|
|
General Lighting Request at 1 City Hall Plz
Please check the control circuit on,SLCB#1285 located Jewish War Veterans Dr.@ Lemuel Shattuck Hospital lights are on constant
CLOSED
Resolved. Crew checked control circuit adjusted photo cell H Tyra C Smith D Leary. -
about 1 year ago
#101003853729
|
|
|
General Lighting Request at 1 City Hall Plz
(redacted)
CLOSED
Resolved. Crew checked control panel and installed new photo cell H Tyra C Smith D Leary. -
about 1 year ago
#101003853710
|
|
|
General Lighting Request at 1 Jewish War Veterans Dr, Jamaica Plain
STRAIGHTEN POLE AND REPLACE SLIPOVER BASE,SLIPFITTER AND L.E.D. ACORN FIXTURE AND TIE IN AS NEEDED | Problem: [Other]
CLOSED
Case Resolved. STRAIGHTENED POLE AND SUB BASE, REPLACED SLIP OVER BASE, ALL HARDWARE AND L.E.D. ACORN FIXTURE AND TIED IN AS NEEDED ALSO BACK FILLED SUB BASE TO GRADE POLE IN DIRT NO PATCH NEEDED. G. Mc CARTHY /J.PETERSON, S.RIED,R. Di BATTISTA / N.MUSTACCHIO. -
over 1 year ago
#101003609890
|
|
|
General Lighting Request at Intersection Of Williams St & Forest Hills St, Jamaica Plain
Missing fixture exposed wires
CLOSED
Case Resolved. CREW MADE CABLES SAFE WILL ISSUE W/O TO REPLACE ACORN FIXTURE. -
over 1 year ago
#101003651980
|
|
General Lighting Request at 1 Jewish War Veterans Dr, Jamaica Plain
STRAIGHTEN STEEL ACORN UNIT AND REPLACE SLIP OVER BASE,DONUT,SPACER, SLIP FITTER AND L.E.D. ACORN FIXTURE AND TIE IN AS NEEDED LP# 23 | Problem: [Other]
CLOSED
Resolved. Straightened out sub base and pole and replaced slipfitter and L.E.D L.E.D acorn fixture and tied in as needed also shimmied sub base with steel plates and back filled sub base to grade no patch needed pole in grass. G.Mc Carthy / J.Peterson / J.Cuniff / N.Mustacchio. -
over 1 year ago
#101003534386
|
|
|
General Lighting Request at 1 Jewish War Veterans Dr, Jamaica Plain
STRAIGHTEN ACORN POLE AND REPLACE L.E.D. FIXTURE AND TIE IN AS NEEDED LP#35 ***** MAY NEED SLIPOVER BASE ***** | Problem: [Other]
CLOSED
Resolved. Straightened out sub base and installed 2 steel plates and also installed new acorn fixture and tied in as needed back filled sub base to grade no patch needed pole in grass. G.Mc Carthy / J.Peterson / S.Ried / N.Mustacchio. -
almost 2 years ago
#101003451924
|
|
|