- ID
- #101002544337
- Status
- CLOSED
- Opened
- Closed
- Description
- When will the city replace the tar with brick sidewalk now that Extanet Systems installed their wireless pole?
- Location
-
Intersection Of Lawrence St And Berkeley St, Boston, Ma
42.34664832, -71.07082694
Activity
-
Submitted
Opened
Closed
Case Resolved | Dear Constituent, The Boston Public Works Department Construction Inspection Unit (CIU) has identified the sidewalk left in asphalt as belonging to Extenet Sidewalks are required to be restored within 60 days. The location has been entered into the CIU data base that tracks repairs to be made by utility companies or private contractors If at anytime the asphalt patch becomes unacceptable before the concrete restoration is made Extenet will be required to make all necessary repairs. The CIU will monitor the progress of the repair. Mark Cardarelli Supervisor of Utility Coordination and Compliance Boston Public Works Department 617-635-4951 Office