ID
#101002930146
Status
CLOSED
Opened
Closed
Description
Last fall the concrete sidewalk was remove and patch with asphalt until the better weather in the spring or summer 2019. That the sidewalk will be refill with concrete. As of 6/10/2019 no one from the city has survey the sidewalk issue.
Location
254 Hebron St, Mattapan, Ma, 02126
42.2711624, -71.1087602
Photos

Activity

  • Submitted

  • Opened

  • Closed

    Case Noted | We have sent an engineer to evaluate and will take care of any immediate public safety hazards. Permanent restoration will be included in a future program when we address upgrades to the area sidewalks. Michael Somers Senior Civil Engineer Construction Management Division Boston Public Works 617-635-3831 Michael.Somers@Boston.gov