Description
Forest hills street and sidewalks are currently being torn up for utility work. When the utility work is done would you please put cement sidewalks in instead of just patching the asphalt? In This section of Forest Hills Street the sidewalks have been a mess for a long time and there aren't any proper ADA transitions between driveways and sidewalk. Thanks!
Location
265 Forest Hills St, Jamaica Plain, Ma, 02130
42.30357661, -71.10350232
Photos

Activity

  • Submitted

  • Opened

  • Closed

    Case Noted | As previously stated, "When construction is finished, the contractor will be required to repair the sidewalk to it's original condition." As far as the depressed driveway, the City has it in our sidewalk repair queue and will address it when we make upgrades to the area sidewalks.