CLOSED #101001687044

Case Resolved. Dear Constituent,

The Boston Public Works Construction Inspection Unit (CIU) Inspector investigated and determined the following:

The sidewalk engineer states that the repair made by the BWSC contractor meets City specifications.

The little chip on one of the adjacent flag that they placed concrete in does not meet the standard of having an entire flag dug out and done over.

The adjacent flags have no major cracking and are not trip hazards.

For any questions or concerns, please contact the number listed below

Sincerely,

Mark Cardarelli
Supervisor of Utility Coordination and Compliance
Boston Public Works Department
617-635-4951 Office.

Opened
10+ y ago
Closed
10+ y ago
Description
Other | The nature of the problem: [Crack in the sidewalk needs to be filled in]
Location
37 39 Mount Vernon St, Dorchester, Ma, 02125
42.32159539, -71.05719166

Activity

  • Submitted

  • Opened

  • Closed