CLOSED #101003298117

Case Resolved. Dear Constituent,

The Boston Public Works Construction Inspection Unit (CIU) Inspector investigated and determined the following:

The utility work is actually in pretty good shape

Its the roadway that needs resurfacing

Recommend you call 311 back and ask that the case be allocated to our roadway repair queue to be inspected by our engineers to possible add to a future paving program

For any questions or concerns, please contact the number listed below

Sincerely,

Mark Cardarelli
Supervisor of Utility Coordination and Compliance
Boston Public Works Department
617-635-4951 Office.

Opened
6+ y ago
Closed
6+ y ago
Description
Street construction was done in September 2019 and although temporary patches were put in place, the road has not been repaved since, and is in bad shape.: [submitted via https://seeclickfix.com/issues/7894818]
Location
14 Cazenove St, Boston
42.34715916, -71.07268884
Photos

Activity

  • Submitted

  • Opened

  • Closed