Reports (211)
-
Bridge Maintenance
What is the nature of the problem: [Constituent reports part of the wall has fallen apart/pile of rubble at the base of the everett st bridge, where everett st seperates into going over the birdge and continuing towards lincoln st.]
OPEN #101004819137 -
-
Bridge Maintenance
What is the nature of the problem: [Constituent requests update on case #4552033, was added to bridge maintenace queue in November 2022 for missing bollard on stairs.]
CLOSED #101004659019Duplicate of Existing Case. 101004552033.
-
Bridge Maintenance
What is the name of the bridge: [Meridian St./Chelsea River: (B-16-019)] What is the nature of the problem: [Constituent states there is a pothole that is on the meridian st brigdge in the right lane near franks autobody shop. Constituent states the pothole is near the electrical pole exiting the bridge. Constituent states he can be contacted for any questions.]
CLOSED #101004658393Resolved. Filled.
-
Bridge Maintenance
What is the name of the bridge: [Meridian St./Chelsea River: (B-16-019)] What is the nature of the problem: [Bpd reports bridge stuck at this location.]
CLOSED #101004611359Noted.
-
Bridge Maintenance
What is the name of the bridge: [Meridian St./Chelsea River: (B-16-019)] What is the nature of the problem: [fwd'd from MassDOT I was on the meridian street bridge in east Boston on Saturday December 3, 2022 at 7:01pm. The bridge had opened up for cars to pass through as I was on the bridge the bridge gate fell on top of my car suddenly hitting the top and back of my vehicle. I would like to talk to someone regarding this incident.]
CLOSED #101004591594Case Noted. Please reach out to the City Clerk's office for all claim related issues. Their phone number is 617-635-4601 or more information and email can be found online at: https://www.boston.gov/departments/city-clerk/how-file-claim-city.
-
Bridge Maintenance
CLOSED #101004545274Case Invalid. No information with case.
-
Bridge Maintenance
What is the name of the bridge: [Summer St./Fort Point Channel: (B-16-031)] What is the nature of the problem: [Constituent states the steel pieces on either side of the bridge in the roadway make a loud banging noise whenever he drives over them, is concerned that they are not stable.]
CLOSED #101004509032Case Noted. No immediate structural concerns. Bridge is scheduled for resurfacing and joint repairs next year.
-
Bridge Maintenance
What is the name of the bridge: [North Washington St./Charles River: (B-16-016)] What is the nature of the problem: [Constituent states she has heard rumors that the wrong rivets were used in this bridge, and that a team from Germany inspected it and advised that the whole bridge needed to be taken down. She would like clarification on this rumor.]
OPEN #101004482850 -
Bridge Maintenance
What is the name of the bridge: [North Washington St./Charles River: (B-16-016)] What is the name of the footbridge: [Rutherford Ave. Footbridge/Ruthford Ave.: (Unknown)] What is the nature of the problem: [Constituent reporting that the footbridge has lots of debris from construction work, and would like for the area to be cleaned.]
CLOSED #101004248485